Bus Bullet NEW DOWNTOWN TRANSIT CENTER:


Here are some preview pictures:

exterior

canopy

hall

 

 

Bus Bullet TRANSIT CENTER TIMELINE:


 

Month Element Description Completed
5/30/2006 Announce move to S. Broadway  
6/5/2006 Design of South Broadway site
1/12/2007 Public Meetings
04/00/07 1st Draft - Determination of Main Street usage and alternate routing  
06/00/07 Final determination of Main Street Usage and alternate routing  
08/00/07 First draft of service revisions
09/00/07 Determination of routes to be interlined
07/00/07 Design to 30%  
     
07/00/07 Board Update  
09/00/07 Public input on building design/ 1st draft of service revisions
10/00/07 2nd Draft of service revisions
10/00/07 Design to 90%  
     
10/00/07 Board Update  
10/00/07 Public input on building design - Friends and Neighbors of facility  
Need TBD Public input on service restructure  
Need TBD 3rd Draft of service revisions  
11/00/07 Final Design  
11/00/07 Out to bid  
12/00/07 Award/Board Approval  
10/22/07 Ground Breaking  
03/00/08 Final draft service revision  
     
05/00/08 Final public hearings  
06/00/08 Board Approval of service changes  
09/00/08 Schedule changes  
10-12/00/08 External training with agencies and public  
11/00/08 Construction Completed  
12/00/08 Move in  
     
01/00/09 Community Celebration  
1/25/2009 Service begins in new center  